Project Description

  • Project name: LPG jetty and pipe corridor
  • Project location: Bonny River, Nigeria
  • Name of client: Arcadis Nederland B.V.
  • Period: 2013 – 2014

Description of the project

Prepare a feasibility study for the construction of a jetty structure in the Bonny river for the unloading of cryogenic/pressurized LPG. The jetty had to be capable of handling vessels in the range of 5,000 to 50,000 DWT.

Apart from studying the optimum location for this jetty along the river banks, a preliminary design was made for the jetty including a land base, access trestle, platform and breasting and mooring dolphins. In parallel alternatives were studied for a pipe corridor through a mangrove area as to connect the jetty with the on shore storage area.

Services provided by Port Consultants Rotterdam

  • Project management
  • Design coordination
  • Technical input for the feasibility study